B1 B3 C2 C4

 The scaffolding tower    Complete documentation

The most popular tower used in construction.

It offers several possible height combinations ( 0,925 m frames or 1,50 m high) for a better shoring.

In addition, several schemes exist for this tower :

  • Scheme A : Tower equipped with a base plate (plaque de base) and an innertube with adjustment head and locking pin.
  • Scheme B : Tower equipped with a base jack and and an innertube with adjustment head and locking pin.
  • Scheme C : Tower equipped with a base jack and a head jack.

This tower load capacity varies between 3 and 4 tons by foot depending on the chosen combination.


The different elements are stored into separate baskets/racks : 
  • Racks for frame with ladder (for frames of 925 or 1500 mm).
  • Grillaged baskets for jacks and accessories.

 

This shoring tower can be easily moved thanks to the 3 wheel trolley, there is no need to use a crane or to remove it.